Key points
- Prabowo said on 13 February 2026 that 1,000 fishing villages would operate in 2026, and 5,000 by 2029.
- KKP said on 4 November 2026 that 100 KNMP were built and operating across 2025 and 2026.
- KKP now targets 2,000 KNMP in 2027; land availability is a recurring obstacle.
- A Rp22 billion KNMP in Jepara could not run fully because a working capital loan was not disbursed.
- Verdict: far off track.
In February 2026 President Prabowo Subianto said 1,000 Red-and-White fishing villages would be operating this year. With six weeks of 2026 left, his own fisheries ministry counts 100.
The promise
"Our target in 2026 is to reach 1,000 [fishing villages], and subsequently our total target by 2029 is 5,000 fishing villages," Prabowo said at the Indonesia Economic Outlook 2026 forum at Wisma Danantara in Jakarta on 13 February 2026, VOI reported. Each village, he said, would get an ice plant, cold storage, a jetty, boats and vehicles, run through a cooperative that repays the investment over 10 to 12 years.
At the same forum, Coordinating Food Minister Zulkifli Hasan said 85 of an initial 100 units were finished and 15 were still being completed. "This year we will complete 1,000 units. For 1,000 units the budget is roughly Rp22.5 trillion," he said, according to a report republished by his ministry.
Verdict: far off track. The deadline has not passed, but the Maritime Affairs and Fisheries Ministry (KKP) says only 100 Red-and-White fishing villages (Kampung Nelayan Merah Putih, KNMP) are operating, a tenth of the 2026 target, and it is now talking about 2,000 in 2027.
What the ministry's own figures show
- On 4 November 2026 KKP director general Yudi Nurul Ihsan said that across 2025 and 2026, 100 KNMP had been completed and begun operating, according to a release on the ministry's website.
- The same day, KKP capture fisheries director general Ridwan Mulyana told detikBali that "100 locations have been operating in 2026". He said KKP targets 2,000 KNMP in 2027 and 5,000 by 2029.
- That 100 matches the size of the first batch Zulkifli Hasan described in February, when 85 of 100 units were finished. We found no published KKP figure for how many of the 1,000 villages planned for 2026 have been built, are under construction or are operating.
Ridwan also named the main obstacle: land. "Fishing communities exist, cooperatives exist, but the land is not available. There is also land available, but few fishers," he told detikBali, adding that land status must be "clean and clear".
What happens on the ground
Built does not always mean working. In Bumiharjo village, Jepara, Central Java, a KNMP that cost Rp22 billion could not operate fully because a Rp1 billion working capital loan requested from KKP's fisheries capital agency (LPMUKP) had not been disbursed after about six months, Radar Kudus reported on 29 May 2026. "Without capital support, these facilities will just be ordinary buildings," said Zainal Anis, head of the village's Red-and-White cooperative, which had about Rp5 million in member savings.
Destructive Fishing Watch (DFW) Indonesia warned in January 2026 that KNMP extension workers and infrastructure were concentrated in Java. It counted 273 extension workers across 65 KNMP sites, with some villages having two and one in the Riau Islands having just one. Without more staff and standard infrastructure, "fishing villages risk becoming policy artefacts", DFW's Luthfian Haekal said, Tempo reported.
The money question
Zulkifli Hasan put the cost of 1,000 villages at about Rp22.5 trillion. KKP's entire budget ceiling for 2026 was set at Rp13 trillion when the 2026 state budget was approved, according to the 2026 ministry work plans (RKA K/L) cited by the fisheries justice coalition KIARA, which said it saw no allocation focused on protecting small and traditional fishers. We did not find a published breakdown of how the Rp22.5 trillion would be financed; Prabowo has said village cooperatives will repay the investment to banks and the government.
The government's side
KKP says the villages are meant to cut fishers' costs, keep catches fresh and raise prices, and it targets lifting the fishers' terms of trade index (NTN) from 103 to 130 in 2027. Ridwan said building is being done in stages and that sites need a fishing community, a cooperative and clear land before work starts.
Why the verdict is far off track
The promise was specific: 1,000 operating fishing villages in 2026. The only operating figure the ministry has published is 100, stated twice on 4 November 2026, and the ministry's planning has already moved to 2027. Unless KKP publishes data showing hundreds more villages coming online before 31 December, the 2026 target will be missed by a wide margin. We will update this check and the promise tracker when new figures appear.
Track this promise: Prabowo's 1,000 fishing villages pledge.
Sources
- 1.VOI: Presiden Targetkan 1.000 Kampung Nelayan Beroperasi Tahun Ini, voi.id
- 2.Kemenko Pangan: Anggaran Rp22,5 Triliun, 1.000 Kampung Nelayan Bisa Terwujud, kemenkopangan.go.id
- 3.KKP: KKP Optimalkan KNMP Untuk Tingkatkan Pendapatan Nelayan, kkp.go.id
- 4.detikBali: KKP Targetkan 2.000 KNMP Dibangun Tahun Depan, detik.com
- 5.Radar Kudus: Pinjaman dari KKP Tak Kunjung Cair, Kawasan Kampung Nelayan di Jepara Belum Bisa Beroperasi, radarkudus.jawapos.com
- 6.Tempo: Manajerial Kampung Nelayan Merah Putih Dinilai Masih Rapuh, tempo.co
- 7.KIARA: Pagu Anggaran KKP Meningkat Menjadi 13 Triliun, kiara.or.id