Key points
- Bakom said on 25 November 2026 that most community activities and basic services in flood-hit Sumatra have resumed.
- Government data show 4,821 of 4,922 schools and all 87 hospitals back in operation.
- Only 2,892 of 60,055 planned permanent homes, 4.8 percent, are finished; the target was 57,027 two weeks earlier.
- About Rp29.9 trillion of a Rp100.1 trillion three-year plan has been disbursed.
- Amnesty found aid cut at village level and about 60,000 people still in uncertainty.
- Verdict: partly true.
Verdict: Partly true. The government's own figures back the claim that most schools, hospitals and health centres in the three provinces are working again. But a year after the floods, fewer than 5 percent of the permanent homes it plans to build are finished, official housing targets keep changing, and Amnesty International found families still waiting for shelter and aid that was cut at village level. "Most basic services" are back; most people who lost their homes are not.
The claim
"A year after the Sumatra disaster, we see that most community activities and basic services have resumed," Muhamad Hidayat, an expert staff member at the Government Communication Agency (Bakom), said in a statement on 25 November 2026, published by Bakom and carried by ANTARA as a press release.
The floods and landslides of late November 2025 hit 53 regencies and cities and 4,533 villages in Aceh, North Sumatra and West Sumatra. More than 2.1 million people were displaced and more than 184,000 houses were damaged, Home Affairs Minister Tito Karnavian, who chairs the recovery task force (Satgas PRR), said on 9 November, the State Secretariat reported.
What the record shows
-
Schools and hospitals are largely back, by the government's count. Of 4,922 affected schools, 4,821 teach in their own buildings, 99 use temporary classrooms and two use other sites. All 87 affected hospitals and 867 health centres are serving patients, though six sub-health centres in Central Tapanuli and Sibolga have not returned to their buildings and will be handled in 2027 to 2028, Bakom said. These figures are the government's own; we found no independent count.
-
Fewer than 5 percent of permanent homes are built. Of a target of 60,055 permanent housing units (huntap), 2,892 are finished, 4.8 percent, and 9,902 more are under construction, the same Bakom statement said. In Aceh alone, 1,758 of 49,184 planned units were finished, the head of the task force's Aceh post, Safrizal, said in a presentation reported by KONTAN on 20 November.
-
The housing target keeps moving. Tito said on 9 November that 57,027 permanent homes needed to be built, Bakom reported. Two weeks later the government's figure was 60,055. Media Indonesia, citing government data to September 2026, reported that only 649 homes had been handed to survivors against a need of 34,777, Media Indonesia reported. Even temporary shelter figures differ: Tito said 20,803 units were built, 99.84 percent of target, while Bakom put it at 20,770 built out of a target of 20,803.
-
Most of the recovery budget has not been spent. The three-year plan for 2026 to 2028 covers 11,520 activities by 23 ministries and agencies and needs about Rp100.1 trillion, of which about Rp29.9 trillion had been disbursed, Bakom said. Safrizal said separately that budget realisation had reached 70 percent as of 18 November, without saying 70 percent of what, KONTAN reported. The 2026 allocation was Rp24 trillion.
-
Amnesty found families still waiting, and aid cut at village level. Amnesty International said on 26 November, after research in 40 villages in Aceh from July to October 2026, that about 57,000 homes are still needed and nearly 60,000 people live in uncertainty. Its regional co-director Montse Ferrer said a Rp450,000 living allowance, paid for only three months, was cut by Rp150,000 at village level for village military officers, police and village officials, and that some residents were asked for fees to have their houses classed as heavily damaged, Tirto reported. These are Amnesty's findings; no court has ruled on them.
-
In parts of Aceh, no government shelter has been built at all. Azharul Husna of KontraS Aceh said that in Langkahan, North Aceh, none of the 23 affected villages had a government-built temporary shelter, and that in one village residents had to rent land themselves to put one up, Tirto reported.
-
Repeat floods are hitting survivors again. Pidie Jaya has flooded nine times since early November 2026, and a flash flood damaged or swept away about 120 houses in Gayo Lues in mid-November, Media Indonesia reported. Of 137 rivers and 38 estuaries slated for normalisation, 36 rivers and seven estuaries were done by November, Bakom said.
The government's side
The Bakom statement itself says recovery is not finished. "The government realises that recovery is not yet complete. Construction of permanent housing for residents who lost their homes is still under way," Hidayat said. It cites weather, the size of the affected area, remote locations and cut roads as reasons for delay, and says rehabilitation will continue until 2028, with about Rp42 trillion proposed for 2027.
Tito said, in remarks KONTAN reported on 20 November, that data would be matched so that no affected resident is left out of aid, and that the process must be accountable "because the aid uses state money". The government says it has paid a waiting allowance (Dana Tunggu Hunian) to 26,761 families, all of its target households.
Context: a claim made against complaints of "100 percent" recovery
The statement came as civil society groups accuse officials of overstating recovery. Rahmad Maulidin of LBH Banda Aceh said the government had hired influencers to claim recovery was "100 percent", Tirto reported; that is his allegation. NewsWLD checked a similar claim by President Prabowo on 11 November and rated it partly true. A coalition of survivors has also filed a citizen lawsuit at the Jakarta administrative court demanding dedicated funding for reconstruction in Aceh, Tirto reported.
Why the verdict is partly true
The part of the claim about basic services is supported by the government's data: schools are out of tents and hospitals are open. But the framing of a year in which "most community activities" have resumed leaves out the largest unmet need. More than 57,000 planned permanent homes are still unbuilt, the official target has shifted by thousands within weeks, under a third of the three-year budget has been disbursed, and independent monitors document aid cuts and areas with no shelter.
What we do not know
- Why the permanent housing target moved from 57,027 to 60,055 in two weeks, and which figure is current.
- What the 70 percent budget realisation figure refers to.
- Whether the aid cuts Amnesty documented are being investigated by the authorities.
Sources
- 1.Bakom: Refleksi 1 Tahun Bencana Sumatera, Layanan Dasar Pulih, Pembangunan Huntap Terus Dikebut (25 Nov 2026), bakom.go.id
- 2.ANTARA: Refleksi 1 Tahun Bencana Sumatera, Layanan Dasar Pulih, Pembangunan Huntap Terus Dikebut (26 Nov 2026), antaranews.com
- 3.Setneg: Presiden Prabowo Gelar Ratas Evaluasi Progres Satu Tahun Pemulihan Pascabencana Sumatra (9 Nov 2026), setneg.go.id
- 4.Bakom: Presiden Prabowo Pastikan Korban Bencana Sumatra Segera Tempati Hunian Tetap, 57 Ribu Rumah Disiapkan (10 Nov 2026), bakom.go.id
- 5.KONTAN: Setahun Satgas PRR, Pemulihan Sumatera Capai 70 Persen (20 Nov 2026), sumaterapulih.kontan.co.id
- 6.Tirto: Setahun Pascabanjir Aceh 60 ribu Warga Masih Hidup Tak Pasti (26 Nov 2026), tirto.id
- 7.Media Indonesia: Setahun Pascabanjir Sumatra, 60 Ribu Penyintas Belum Memiliki Hunian Tetap (28 Nov 2026), mediaindonesia.com
- 8.NewsWLD: Fact check: Prabowo says many disaster-hit Sumatra areas have fully recovered, newswld.com