“Pramono targeted completing the acquisition of 170 plots of land for the Ciliwung river normalisation by the end of 2026: "Thank God, of the target of 170 plots, 62 have now been completed." He said that if the land target is met this year, normalisation in the Cawang area would start in 2027.”
as Governor of Jakarta · Said 10 Jul 2026 at Cawang, East Jakarta
Source: Pramono Kebut Pembebasan Lahan Normalisasi Ciliwung, Target Selesai Akhir Tahun · Liputan6.com
Our assessment
Not assessed yet: the deadline has not passed or there is no verified figure.
Every status change and progress update, newest first, with its sources.
13 Nov 2026 · Progress update
Nov 2026: six weeks before the deadline, 97 plots in Cawang and Cililitan were still not acquired, and Pramono asked the land agency (ATR/BPN) to speed up acquisition and the site determination. The province has not published a single updated count against the 170 plot target.